general planning
Revitalization of the indoor and outdoor swimming pools – Competition entry
gobli architecs & engineers, together with GBT Planung GmbH, were commissioned by the municipality of Amstetten to design the new municipal swimming pool in Amstetten as the general planning team.
The existing indoor swimming pool was replaced by a new building, with essential technical areas being retained and renovated. In addition to the indoor pool, various functions were added, such as catering facilities, outdoor pools, and, above all, a play area in the form of a riverside park.
The project was expanded to include another building for catering facilities and club rooms.
The project was constructed with high standards of sustainability and cost-effectiveness. Particular emphasis was placed on durability and low operating costs, especially in the choice of materials and technical equipment.
The general planning team delivered a magnificent project in a very short construction period.
Key data of the project
Site area: 30,470 m²
Gross floor area 9,500 m²
Net usable area 7,845 m²
Water area 880 m²
PV system 460 KWp
Diving platforms 1 m / 3 m / 5 m
Water slide: Outdoor wide water slide: length 13.5 m
Indoor tube slide: length 70.9 m
Restaurant: indoor/outdoor guests 100/150
Indoor buffet: catering for indoor pool operations
Outdoor buffet: for summer operations and catering for up to 1,600 guests.
Water play park: 240 m² of fun for little ones and toddlers
Shore park: play park approx. 6,000 m²
Volleyball courts, fun park, motor skills and play
Participating partner companies:
Local construction supervision for building services: Concept ³ – Wolfgang Üblacker GmbH
Fire protection planning: Firenet Service GmbH
Electrical engineering planning: TB Freudenthaler GmbH
Building services and bathroom planning: GBT Planung GmbH
Drainage planning: IKW ZT GmbH
Construction site coordination: Baumeister Kern GmbH
Structural engineering: Peter Mandl ZT GmbH
Building physics: DI Dr. techn. Roland Müller
Construction management: PSB Planung-Statik-Bauleistungs GmbH