submission of the approval planning and execution planning, tendering, safety coordination according to BauKG (Austrian Construction Coordination Act)

Building of a transformer station

For Alstom, Gobli architects & engineers was responsible for the structural planning and construction of a transformer station at the wind farm in the municipality of Pottendorf in Lower Austria.

In addition to the construction of the actual transformer station, the main challenge of this project was the related needed expansion of the infrastructure. Separate access roads had to be built to transport the transformer. These services were also supervised and carried out by Gobli architects & engineers.

 